It’s been a good week, and it’s not even over yet. Much gratitude is due the entire team as we move into a Friday with many moving parts and a growing balance sheet of synchronous progress in the icehouse, outside the icehouse, and throughout Rosslyn’s still muddy but increasingly springlike grounds.
A photo essay (think more photos, less essay) will offer the best glimpse into the latest round of accomplishments. And behind all of these photos — if not literally behind the camera, in all cases behind the wrangling and tasking and managing and juggling and multitasking and quality control — is Pam Murphy. Our gratitude to everyone behind this week of synchronous progress, especially the woman who keeps it all together!
In the photo above installation of the T&G nickel gap on Rosslyn’s icehouse ceiling is. Almost. Done. Rumor has it that tomorrow the ceiling will be finished. Fingers crossed!
March has marked plenty of plumbing progress in the icehouse rehab, most recently installation of the admittedly unattractive but practical mini split that will keep this oasis cool in the steaming days of summer.
Electrical headway includes reinstallation of the lamp next to the entrance door. Removed during installation of the insulated panels and clapboard siding, the patinated exterior sconce is now back in place.
The first of the Marvin Doors have been received from Windows & Doors by Brownell. We started the process back in August, and the still have a little over a month to wait for all of the windows. So for now we’ll get to work painting the doors and installing them. On the right of the photo is an old door that Peter has rebuilt and that is now repainted in satin White Dove by Benjamin Moore to match the rest of the icehouse interior trim.
In other exciting spring news, Tony has done a remarkable job of preparing the high tunnel for early season planting. And check out that solar gain on a freezing day!
In addition to carpentry, plumbing, electrical, and gardening headway, some landscaping progress is also worth noting. In the photo above the lawn adjacent to the icehouse deck and terrace, has been crisply edged so that Bob Kaleita can fine-tune the site work and stone wall construction can begin.
A hat tip to our Amish neighbors who’ve accelerated the landscaping grounds work AND split up the massive ash tree that fell a couple of weeks ago. Plenty of firewood now curing, a geometrically impeccable extension to the daylily bed, and plenty of edging including the new hemlock hedge planted last summer by Patrick McAuliff.
Crisp edging ready for mulch along the hemlocks. In the photo above the perspective is looking east toward Lake Champlain, and in the photo below looking west toward the Adirondacks.
And that’s just *part* of a busy week. Thank you, team!
Leave a Reply